القصة
One of the contractor PPE Clothing caught a serious fire burn from the sparks while grinding and preparing steel plates. basically because the clothing had traces of epoxy glue(perhaps some acetone/thinners as we used them together to either make it malleable or to clean it off).So when the sparks fire were bouncing on the clothing was able to catch flames quickly
My advice
Even when the HSE part or identifying of hazards the fire equipment should be placed so close or ready as if you anticipating things to go wrong. Because as much as they were available the whole incident caught everyone off guard that 10 seconds delay was enough to cause serious burns




انضم إلى النقاش
هل مررت بموقف مشابه؟ شارك رأيك أو اطرح سؤالاً. تسجيل الدخول أو أنشئ حساباً مجانياً.