Working as an Execution Supervisor on an IBS installation project at Saudi Aramco’s Jafurah Gas Facility was an important learning experience in my professional journey.
Although the project was initially planned for 45 days, several challenges extended the execution period beyond three months. These included access approvals, inadequate initial site surveys, equipment and resource planning, safety documentation, electrical interface requirements, and interdepartmental coordination.
My advice
Proper site surveys are the foundation of successful execution.
Administrative and access requirements must be addressed in advance.
Safety planning should be integrated into every project activity.
Resources must be selected according to actual site conditions.
Effective communication and coordination between departments are essential.
Every challenge should become an opportunity for improvement.