Production Stopped Before It Started

During an IBS project, production stopped for two days because the contractor requested panel fabrication before obtaining the final consultant approval.

The factory was ready, manpower was available, but manufacturing could not proceed.

Lesson learned:

In IBS projects, every day of approval delay can impact fabrication, delivery, and installation activities.

Always secure approvals before booking production slots.

#FieldExperience #IBS #ContractorManagement

izahedah

Leave a comment Cancel reply

Your email address will not be published. Required fields are marked *

Recent Posts

  • Testing Revealed What Installation Could Not
  • A Small Drawing Error Became a Site Problem
  • Weekly Meetings Solved More Problems Than Emails
  • The Best Contractor Was Not the Cheapest
  • One Activity Delayed an Entire Project

Recent Comments

No comments to show.
© 2026 ZAHEDAH