During an IBS project, production stopped for two days because the contractor requested panel fabrication before obtaining the final consultant approval.
The factory was ready, manpower was available, but manufacturing could not proceed.
Lesson learned:
In IBS projects, every day of approval delay can impact fabrication, delivery, and installation activities.
Always secure approvals before booking production slots.